Kahlberg Wind Park, Hesse

This project had a number of uncertainties in store for wiwi consult during its supervision of the construction. The heavy onset of winter, for example, negatively impacted upon the construction work at this forest location as the difficult approach route, with a 15% incline, became impassable in certain points. Snow-clearing measures and repairs to the park infrastructure were necessary on a daily basis and over many weeks.

Furthermore, the start of construction and deliveries only took place after lengthy delays and under minimal space conditions at the site at the minimum. It was only thanks to an ingenious storage concept and by establishing a one-way traffic system that it was possible to achieve something for which the space was not actually there: the interim storage of all components directly in the wind park.